Buyer Guide

Factory Acceptance Test for Machinery Orders

A machinery factory acceptance test should verify the exact ordered equipment against an approved specification before release, packing or final payment. It is not just a start-up video. Agree the test procedure, material, duration, measurements, acceptance limits, witness method, report and correction process before the machine is built. Keep site-dependent items separate for later commissioning or site acceptance.

Distinguish a FAT from a supplier demonstration

A demonstration shows that a machine can move or produce something. A FAT compares the exact machine with an approved requirement and records results. The procedure should identify the equipment, test setup, participants, instruments, criteria and evidence.

Supplier demonstrationControlled FAT
Supplier chooses convenient materialBuyer-approved material or documented substitute
Short edited videoWitnessed sequence with continuous records where needed
Machine starts and runsOutput, quality, faults and safety functions measured
No controlled baselineApproved specification, drawings and test revision
Verbal passSigned result, punch list and release status

Approve the FAT protocol before the machine is ready

IEC 62381 provides a framework for FAT and related acceptance tests in industrial automation, including agreement on scope and responsibilities. It does not supply product-specific acceptance limits. Adapt the plan to the actual machine, process and destination.

  • Purpose, scope and exclusions
  • Exact machine and controlled document revision
  • Test material, quantity and preparation
  • Utilities, fixtures, instruments and calibration status
  • Test sequence, duration and sampling
  • Pass, conditional pass, fail and retest rules
  • Witness attendance, remote access and recording
  • Required report, data files and signatures

Keep FAT separate from the Machinery Installation and Commissioning Checklist for site conditions that cannot exist at the supplier's factory.

Confirm readiness before scheduling the FAT

Ask the supplier to confirm assembly completion, software readiness, guards, documentation and test material before a buyer or inspector travels. Request current photos and a readiness checklist. Do not accept a test on a different machine unless the purpose and remaining uncertainty are explicit.

  • Machine available and not packed
  • Approved options and components installed
  • Required utilities and test fixtures available
  • Supplier operators and engineers scheduled
  • Measurement equipment ready
  • Known open issues disclosed
  • FAT procedure and acceptance limits signed off

A readiness check reduces wasted visits but is not the FAT result.

Verify machine identity and configuration

Match the equipment to the purchase order, drawings and approved component list. Record serial or project identifiers, overall dimensions, critical assemblies, electrical ratings, controls, software versions, options, guards and supplied accessories.

Photograph nameplates and critical components where appropriate. If a substitution was approved, confirm that drawings, spares and manuals reflect the delivered version.

Test performance with representative material

Run enough material to reach stable operation and expose recurring faults. Record operating settings, accepted output, rejects, scrap, stops and interventions. Test the meaningful product range rather than only the easiest size.

Test areaEvidence
OutputAccepted units or mass per defined time under stated conditions
QualityMeasured dimensions, fill, finish or other agreed criteria
StabilityRun duration, stops, alarms and recovery
ChangeoverTime, people, tools and first acceptable output
Reject handlingDetection, removal and count accuracy
DataRecipes, counters, alarms, logs and export where required

When real material cannot be used, record exactly what the substitute fails to prove.

Check safety functions and maintenance access

Test guards, interlocks, emergency stops, restart behavior, alarms and safe access that are within the agreed FAT scope. Destination rules and machine-specific standards determine the complete requirement; a generic checklist is not a compliance assessment.

Review isolation points, clearing of jams, cleaning, lubrication, wear-part access and normal maintenance. The supplier should provide instructions consistent with the delivered configuration.

Review documents, software and spares before release

  • Approved and as-built drawings
  • Electrical and utility diagrams where applicable
  • Operation, maintenance, safety and cleaning manuals
  • Component and spare-parts lists
  • PLC/HMI backup, passwords and software-license scope when included
  • Declarations and reports required for the destination and machine
  • FAT data, photos, video and signed result
  • Packing, lifting, center-of-gravity and disassembly instructions

Document delivery can be an acceptance gate. Do not let essential records remain a promise after shipment.

Control failures, punch-list items and retesting

Classify findings by their effect on safety, mandatory performance, delivery and documentation. State who corrects each item, the due date, evidence required and whether full or partial retesting is needed.

  • Pass: all release criteria satisfied
  • Conditional pass: only defined non-critical items remain with an approved closure plan
  • Fail: mandatory performance, safety or configuration criteria not met
  • Not tested: scope could not be demonstrated and remains open

Use cautious release language. A signed FAT record should not waive warranty or hidden defects unless a qualified contract reviewer confirms the effect.

Choose on-site, remote or independent witnessing

Buyer attendance can support technical decisions, while an independent inspector may provide local witnessing and records. Remote video can be useful when the camera plan, continuous sequence and measurement evidence are controlled. None of these automatically replaces qualified engineering review.

When using an inspection company, provide the approved specification and FAT protocol. A generic pre-shipment inspection should not be presented as a complete machine performance test.

FAT release decision

Release should depend on the agreed criteria, closed critical findings and delivered evidence. Link commercial milestones only to terms that are written and workable for the project. The broader Mechanical Equipment Sourcing Strategies guide connects FAT to supplier review, payment and shipping.

Copy-ready workflow

Copy Factory Acceptance Test Checklist

  1. Confirm the exact machine, serial identity and approved revision.
  2. Verify assembly completion and FAT readiness before travel or booking.
  3. Use agreed product material or document the substitute limitation.
  4. Check configuration, components, utilities and software versions.
  5. Run output and quality tests under defined operating conditions.
  6. Record downtime, alarms, rejects, scrap and operator interventions.
  7. Test guards, interlocks, emergency stops and safe restart behavior.
  8. Review changeover, cleaning, maintenance and access where relevant.
  9. Collect measurements, photos, continuous video and signed results.
  10. Create a punch list with owner, due date, retest and release status.
  11. Confirm manuals, drawings, backups, spares and packing evidence.
  12. Do not release final balance or shipment solely on unresolved verbal promises.

FAQ

What is a factory acceptance test for machinery?

It is a documented test of the exact ordered equipment against approved specifications and objective acceptance criteria at the supplier's facility before release or shipment.

Is a machine test video the same as FAT?

No. Video may be evidence within a FAT, but the test also needs controlled scope, conditions, measurements, criteria and a result record.

Should FAT use the buyer's real material?

Use representative material when practical. If a substitute is necessary, document what it proves and what remains uncertain.

Does FAT replace site acceptance or commissioning?

No. Site utilities, integration, installation and sustained operation may require separate commissioning or site acceptance tests.

Can final payment be linked to FAT?

It can be a commercial milestone when clearly agreed, but the payment structure and legal effect require project-specific review.

Sources & Further Verification

Use these sources to verify the material responsibility, customs, operational or buyer-risk statements on this page. Destination rules and provider schedules can change. CN Sourcing Tools is not affiliated with the publishers.

IEC 62381:2024 - Factory acceptance test, site acceptance test, and site integration test

International Electrotechnical Commission

A FAT should use an agreed procedure, responsibilities, records and objective acceptance criteria before release.

Open source

ISO 12100:2010 Safety of machinery - General principles for design - Risk assessment and risk reduction

International Organization for Standardization

Safety-related acceptance criteria should derive from defined machine limits and risk-reduction requirements.

Open source

Buying new machinery

UK Health and Safety Executive

The buyer should verify the supplied machine, instructions and safety information before putting equipment into use.

Open source

Regulation (EU) 2023/1230 on machinery

European Union

EU machinery obligations may affect the technical documentation and conformity evidence reviewed before shipment.

Open source

Optional page feedback

Was this guide useful?

Your selection helps prioritize future guide updates. No message or contact information is collected.

This checklist is general sourcing guidance. A qualified engineer, safety professional and destination-market specialist should define and witness machine-specific acceptance and compliance tests.